 |
Time Critical Removal Action,
Dioxin Contaminated Soil
AmDyne performed a Time Critical Removal Action (RA) of burned
soil material contaminated with polychlorinated dibenzo-p-dioxins
(dioxins) located at the Letterkenny Army Depot (LEAD). A total
of 415 tons was excavated and disposed of as part of this effort.
After excavation, the waste soil material was immediately loaded
into tandem-axle dump trucks and transported to a state-approved
landfill. All waste material was disposed of as Residual Waste
according to PADEP regulations. Confirmatory samples were collected
and analyzed by an off-site USACE-approved laboratory for dioxins.
The site was then restored back to natural grade and all equipment
demobilized. |
| |
|
| |
Lead Stabilization and Removal Action
AmDyne provided full service environmental management to a CERCLA
Removal Action at Letterkenny Army Depot. This site was contaminated
with lead at concentrations that exceed risk-based standards.
The site was used for the storage of solid metal ingots (copper,
nickel, and lead ingots). The ingots were not covered and therefore
precipitation ran directly from the surface of the ingots to
the ground. This task involved performing waste characterization
to segregate waste streams for handling and disposal. In addition,
this effort involved excavation, transporting and disposal of
waste, as well as confirmatory sampling and site restoration.
AmDyne proposed an innovative, In-Situ stabilization technique
( Eco-Bond ) to treat lead contaminated
soil at hazardous concentrations and rendered the waste non-hazardous,
resulting in tremendous disposal cost savings. |
| |
|
 |
Remedial Action of VOC Contaminated Soil
AmDyne provided technical, environmental, engineering, and construction
services to the Corps of Engineers, Baltimore District in order
to complete a removal action of soils contaminated with Volatile
Organic Compounds (VOCs) and restore the site for future construction
activities. This project included submittal of all plans, designs,
drawings, specifications and procedures for client and regulatory
approval prior to starting the work. AmDyne provided overall
management to this complex effort, which was completed on a
short time frame to accommodate future constructions at this
site. |
| |
|
 |
UST Removal and Replacement, Bolling
AFB
AmDyne was responsible for securing all required permits to
remove and replace (3) 10,000 - gallon steel underground fuel
storage tanks and replace with (2) new 10,000 - gallon double-wall
fiberglass fuel storage tanks and integrate them into the
existing fuel management system. AmDyne provided a complete
set of project drawings in AutoCAD and Specifications in the
CSI 16-Division format using Specsintact. AmDyne was also
required to provide a sheeting/shoring plan, de-watering plan,
demolition and removal of existing concrete slab, excavation,
disposal and new construction.
AmDyne provided on-site Quality Assurance and oversight throughout
construction activities including plans and specification
development, shop drawing and equipment submittal reviews
and construction daily reports. Soil and water samples were
taken prior to excavation, backfill and tank closure reporting.
Tank and piping leakage tests were made before and after tank
placement and final tank precision testing. Blockage and pressure
decay test for the vapor recovery were made prior to the dispensers
returning to service. Final site restoration included replacing
the concrete slab to match the existing reinforced slab, curb
and gutter replacement and restoration to disturbed grass
areas.
AmDyne provided red-lined as-built drawings, tank closure
reports and a fuel management system technician for start-up
and system operation check |
| |
|
 |
Removal/Installation of Storage Tanks
AmDyne provided technical, environmental, engineering
and construction services to the Veteran's Administration
in order to assist in the removal and closure of old underground
storage tank systems at Quantico National Cemetery and Baltimore
National Cemetary. AmDyne handled all permitting and utility
clearances, orchestrated the removal of USTs, performed excavation
of contaminated soil, oversaw the restoration of all grading
and landscaping, installed new ASTs and associated equipment,
and performed all required soil sampling, testing and reporting
required for site closure in the States of Virginia and Maryland.
|